Sourced from official Tacoma-Pierce County Health Department (TPCHD) and Pierce County Planning & Public Works program information — last checked July 2026.
Quick answer: converting a property from septic to public sewer in Pierce County requires approval from both Tacoma-Pierce County Health Department and Pierce County Planning & Public Works before a sewer permit is issued. You must apply to decommission your septic tank before any pumping happens. If your home was built with an interim septic system on a “dry lines” street, you’ll get a 180-day window to connect once public sewer service reaches you.
Why This Comes Up: “Dry Lines” Neighborhoods
Some Pierce County developments were built before public sewer service reached them. In these cases, the county required builders to install interim on-site septic systems while also laying the sewer mains that would eventually connect the neighborhood — these are called “dry lines,” since the pipe is in the ground but not yet connected to the public system. There are currently 31 such developments in the Pierce County Sewer Service Area. Once sewer service becomes available, the county notifies affected property owners, and homeowners get 180 days (6 months) to complete the connection and properly decommission their septic system.
The Conversion & Decommissioning Process
Based on TPCHD and Pierce County Planning & Public Works’ published conversion requirements. The decommissioning application must come before any pumping.
The single most important rule: your septic decommissioning application must be submitted to the Health Department before any septic tank pumping occurs — not after. Applications are submitted through TPCHD’s online permit system under “On-Site Sewage” → “Septic Tank Decommissioning.” A certified O&M firm approved for pumping must remove the septage, and a site plan showing the decommissioned tank’s location is filed along with the applicable fee. Once your sewer connection is approved and the tank is properly decommissioned, you’ll schedule a sewer inspection and upload your Septic/Pump Tank Decommissioning Certificate to your online application (or email a copy).
Financial Help: Tacoma’s Septic Amnesty Program
If you’re within City of Tacoma limits, converting within two years of public sewer becoming available to your residence qualifies you for a 50% reduction in sewer LID assessment fees or charges-in-lieu-of-assessment — up to a maximum of $10,000. This offer expires two years after sewer becomes available, so it’s worth acting on sooner rather than later. Tacoma’s Environmental Services Sewer Conservation Loan Program also offers low-interest loans for side sewer rehabilitation or reconstruction projects within city limits.
What Happens If You Don’t Convert
Continued use of an on-site septic system after public sewer becomes available — without completing the required decommissioning and connection process — runs against Pierce County’s sewer use code. Beyond the compliance risk, waiting past the amnesty window (if you’re in Tacoma) means losing access to a meaningful fee reduction for no real benefit.
Notified that sewer is available to your property, or not sure where to start? Connect with a local licensed septic provider.
Prefer Email? Send Us a Message
Not ready to call? Leave your info and a local licensed provider will follow up.
Every guide on this site, compiled into one printable document. Enter your email and we’ll send it your way — plus occasional reminders when it’s about time for your next inspection or pumping.
Thanks — here’s your guide:
Download the PDF GuideFrequently Asked Questions
Do I need approval to convert from septic to sewer in Pierce County?
Yes — a sewer permit involving a septic-to-sewer conversion requires approval from both Tacoma-Pierce County Health Department and Pierce County Planning & Public Works before it can be issued.
Can I pump my septic tank before applying to decommission it?
No — the decommissioning application must be submitted to the Health Department before any septic tank pumping occurs.
What is a "dry lines" property?
It’s a home built with an interim septic system while the public sewer main was laid nearby but not yet connected; owners get a 180-day window to connect and decommission septic once sewer service becomes available.
Is there financial help for converting from septic to sewer?
City of Tacoma’s Septic Amnesty Program offers a 50% reduction in sewer assessment fees (up to $10,000) if you connect within 2 years of sewer becoming available; low-interest loans are also available through Tacoma’s Sewer Conservation Loan Program.
Who has to pump and decommission my septic tank?
A certified O&M firm approved for pumping must remove the septage as part of the required decommissioning process.
What do I need to submit after decommissioning is complete?
A Septic/Pump Tank Decommissioning Certificate, uploaded to your online Health Department application or emailed, along with scheduling a sewer inspection.